BASIC ENGINEERING LTD.

COMPLETED PROJECTS

EXECUTED PROJECTS BY BASIC ENGINEERING LIMITED IN BANGLADESH

CLIENTS

CONTRACT VALUE (BTD)

EQUIVALENT VALUE IN UDS (APPROX.)
COMPLETION DATE
Name of project: Installation works including testing and commissioning for Construction and expansion of distribution network for Dhaka Power Distribution Company of Lot-1 (North Zone) Employer/End User: Dhaka Power Distribution Company Limited (DPDC)
483,699,886
May-19
Name of project: Installation works including testing and commissioning for Construction and expansion of distribution network for Dhaka Power Distribution Company of Lot—2 (South Z one) Employer/End User: Dhaka Power Distribution Company Limited (DPDC)

306,010,972

May-19
Supply of Fender, Mooring Bollard and Frontal System for LPG satellite plant at Kolinga, Rupganj, Narayanganj
Petromax LPG
10,200,000
$ 124,390
Apr-19
Installation of 1000mm dia Raker & Vertical pile with Permanent Full Steel Casing Fix Dolphin Jetty at Karnaphully River, Chittagong
Soya Products Bangladesh Ltd, a subsidiary of United Group
36,500,000
$ 1,402,439
Mar-19
Installation of Fixed Platform at Barabkunda, Sitakunda
BM Energy (BD) Ltd
115,000,000
$ 1,402,439
Mar-19
Construction of Civil Foundation, Erection, Testing and Commissioning of 230kV Double Circuit Power Evacuation Line for Summit Gazipur II 300 MW power plant Project, Kodda, Gazipur
Summit Gazipur II Power Limited
72,593,411
$ 885,286
Apr-18
Construction, Erection, Testing & Commissioning of 132kV Double Circuit Power Evacuation Line for Summit Gazipur 149 MW Power GenerationProject, Kodda, Gazipur
Ace Alliance Power Limited
32,199,391
$ 392,676
Apr-18
Installation Works including Site Survey & Drawing, Design of Tower Foundation Testing & Commissioning of Chakaria-Matarbari 132kV Single Circuit Transmission Line on Double Circuit Tower
Angelique International Ltd, India
108,469,400
$ 1,322,798
Mar-18
Stringing of Phase Conductors (Twin Bundle) including OPGW & Earthwire on the line, Length-42 Rt-km under Ashugonj-Bhulta D/C 400kV transmission Line
KEC International, India
29,261,400
$ 356,846
Jun-17
MPA Vessel Berth Jetty Renovation Works including installation of Fender System at Mongla, Bagerhat
Navana CNG Limited (LPG Unit)
60,124,181
$ 733,222
Apr-17
Dismantling the 132kV existing line and Fabrication, Erection, Testing and Commissioning of 132 KV double circuit line under Summit Barisal 110 MW Power Plant
Summit Power, Bangladesh
4,000,000
$ 50,000
Jan-16
Stringing & other associated activities in 132kV Comilla (N) to Comilla (S) T/L under Tripura (India)-Comilla (South) Substation (Bangladesh) Grid Interconnection Project
KEC International, India
7,920,000
$ 99,000
Jan-16
Water intake construction, sheet piling works, dewatering system & associated works at Ashuganj Power Plant water intake project, Ashuganj, Bangladesh
TSK company (Spain)
75,962,157
$ 949,527
Dec-15
Strengthening of existing jetty at Mongla cement factory, Mongla, Bagerhat
Sena Kallyan Sangstha, under Bangladesh Army
107,025,000
$ 1,374,233
Aug-15
Bibiyana Expansion Project, Main Civil Works, Sylhet, Bangladesh. (Cable trenching works, Duct Bank, CPVC Pipe works, HDPE pipe works )
Chevron Bangladesh
717,770,860
$ 8,972,135
May-15
Design, Supply, Iinstallation, Testing and Commissioning of 132 kV Overhead Transmission Line under “Energy Efficiency Program-II, DPDC, Bangladesh
LTB Leitungsbau GmbH, Germany
228,100,000
$ 2,815,286
Apr-15
Supply Heavy Equipments for lifting & handling Construction Project
Plexal Group, Thailand
28,000,000
$ 359,897
Feb-15
Foundation construction, Erection & Stringing of Nine (9) towers for 230 kV Transmission line across Tetulia River (5.5 km) in Barisal under PGCB
KEC International, India
767,433,116
$ 9,864,178
Feb-15
Bibiyana Expansion Project - PABC (accomodation block), Sylhet, Bangladesh
Chevron Bangladesh
114,948,751
$ 1,478,440
Dec-13
Bibiyana South Pad Dyke Repair Construction, Contract # 812590
Chevron Bangladesh Block Twelve, Ltd.
110,286,871
$ 1,477,386
Jul-11
Periodic Road Maintenance Component Contract # 4 for Periodic Maintenance of i) Barobari-Burimary, National Road (N509) 104,630 km under Road Network Improvement & Maintenance Project-I (RNIMP-I)
Roads and Highways Department
163,683,235
$ 2,358,548
Aug-10
Periodic Road maintenance of Kurigram-UlipurChilmari Road, Contract # PRMC-RZ-7
Roads and Highways Department
58,368,388
$ 845,918
Dec-09
Design-build and turnkey construction of 132 kV Double Circuit Aminbazar-Savar Transmission Line, length of line 25km, nos. of tower, 80 nos.
Power Grid Company of Bangladesh
131,683,509
$ 1,908,456
Jul-09
Carrying out Cast-in situ piling (Marine) at Dapdapia Bridge, Barisal
MBEC-PBL-COPRI JOINT VENTURE
42,740,894
$ 623,954
Oct-08
Road Maintenance and Improvement Project, DhakaChittagong Road, Bangladesh, Milling and cold-in situ Re-cycling and overlay works, (Total 41.38 km) executed by NAZIR-BASIC JV
Roads & Highways Department
529,058,945
$ 8,397,761
Jun-07
PMP 2005-06/C048 (Bituminous Carpeting work) at Rupsha , khulna&Terokhada, Mollahar
Roads & Highways Department
15,904,220
$ 244,680
Dec-06
Installation of Test Pilling Work at JattrabariGulistanFlyover.Dhaka, Bangladesh
Dhaka City Corporation
20,000,000
$ 307,692
Oct-06
Emergency Flood Damage Rehabilitation Project, Contact no.: EFDRP/SZ/HBG/Z-01
Roads & Highways Department
16,920,436
$ 260,314
Sep-06
Construction of 100 meter Oxbow lake Bridge at Bibiyana Gas field, Sylhet, Bangladesh
UNOCAL Bangladesh Ltd.
45,000,000
$ 692,307
Jul-06
Strengthening of 2 (two) nos. Bridges at Bibiyana Gas Field, Sylhet, Bangladesh
UNOCAL Bangladesh Ltd.
13,036,303
$ 200,558
Jan-06
Improvement of 2 nos. LGED Bridge at Enayetgonj Bazar
Chevron Bangladesh
12,792,000
$ 196,800
Jan-06
Construction of drilling pad for the rig at Chattak East & earth work layer by layer with watering & compaction by roller &vibrocompactor at Chattak East road
NIKO RESOURCES (BD) LIMITED
48,850,000
$ 751,538
Jan-06
Casing Installation work at Production Pad & Relief Well of Chattak Gas Field, Sunamganj, Sylhet, Bangladesh
Niko Resources (Bangladesh) Ltd.
7,551,959
$ 131,338
Nov-05
Construction of Foundation, piling work and Erection of Generator room, Shelter room, Guardroom, Boundary wall etc. for Microwave Tower and related works at Sitakunda&Wahedpur, Chittagong, Bangladesh.
Orasinvest (BD) Ltd.
10,384,369
$ 180,597
Nov-05
Strengthening of existing pavement of SylhetFenchuganj-RajnagarMoulvibazar-Srimongal-Shaistagonj-Teliapara-Jagadishpur Road (With link to Sherpur) under Habiganj Road Division of Sylhet Road Circle, Sylhet during the year 2004-2005, Contract No. 01 (One)/2004-2005/SE/SRC, Sylhet, Bangladesh
Roads & Highways Department
107,045,047
$ 1,861,653
Nov-05
Casing installation at Bibiyana North Pad Location, Sylhet, Bangladesh
UNOCAL Bangladesh Ltd.
5,806,024
$ 100,974
Oct-05
Land Development and Slope Protection work at proposed Khulna 230/132 kV Substation, Batiaghata, Khulna; Contract No. 01/PGCB/ Sec/2004/2550, Khulna, Bangladesh, Land Development work
Power Grid Company of Bangladesh Ltd.
28,364,466
$ 493,295
Oct-05
Construction of Drilling Pad of Chattak Gas Field, Sunamganj, Sylhet, Bangladesh
Niko Resources (Bangladesh) Ltd.
18,700,000
$ 325,217
Sep-05
Construction of 3 nos. Bridge at Chhatak East Road, Chhatak Gas Field, Sunamganj. Sylhet, Bangladesh
Niko Resources (Bangladesh) Ltd.
12,904,860
$ 224,432
Sep-05
Electrical instrumentation and installation work at Lafarge-Surma Cement Plant, Sylhet, Bangladesh
Larsen & Toubro Limited, India
2,505,403
$ 43,572
Aug-05
Periodic Maintenance Program 2003-PMP-2/2003-2004, Package No. PMP 2003-2004/C49 under Roads and Highways Department, Barisal, Bangladesh
Roads & Highways Department
22,643,855
$ 393,806
May-05
Construction of Barapukuria-Rangpur 132 KV Double Circuit Transmission Line
HG Power Transmission SdnBhd, Malaysia
30,564,000
$ 531,547
Mar-05
Strengthening of existing pavement of MoulvibazarSrimongal-Shaistagonj-Teliapara-Jagadishpur Road (With link to Sherpur) under Moulvibazar Road Division of Sylhet Road Circle, Sylhet during the year 20032004, Contract No. 02 (Two)/2003-2004. SE/SRC, Sylhet, Bangladesh
Roads & Highways Department
196,130,796
$ 3,410,970
Mar-05
Strengthening of existing pavement of Moulvibazar-Sreemongal, Sylhet during the year 2003-2004, Contract No. 03 (Three)/2003-2004. SE/SRC, Sylhet, Bangladesh
Roads & Highways Department
167,098,115
$ 2,906,054
Feb-05
Piling work at Lafarge-Surma Cement Project, Sylhet, Bangladesh, Construction of cast-in situ bored piling work with Rotary Rig, 1200mm, 1000mm, 800mm and 600mmdia
Larsen & Toubro Limited, India
89,288,628
$ 1,566,467
Dec-04
Construction of Foundation and Erection of Microwave Tower and related works, Magura, Bangladesh, Castin-situ bored piling of dia600mm, construction of foundation, erection of tower
Pacific Bangladesh Telecom Ltd.
31,070,946
$ 545,104
Oct-04
Carrying out Bored cast-in-situ pilling work with Rotary Rig at Lafarge Surma Cement Plant Project, Chatak, Sylhet
Larsen & Toubro Limited, India
113,226,897
$ 1,986,436
Aug-04
Improvement of 9 (Nine) Intersections in Dhaka City, Dhaka, Bangladesh, Asphalt Overlay and footpathmedian development.
Roads & Highways Department
290,163,688
$ 5,090,591
Jul-04
Introduction of Circular Waterways around Dhaka City, 1st Phase: Improvement of Navigation and Providing Landing Facilities from Sadarghat to Ashulia Bridge. Work done by Basic Engineering - Basic Dredging JV.
BIWTA
16,400,000
$ 287,719
Jun-04
Maintenance Dredging in the Pussur River Channel of Mongla Port (2.8 million cubic meter)
Mongla Port Authority
415,126,000
$ 7,282,912
Feb-04
Dredging work of the Rivers Buriganga and Turag connection with the Project “Introduction of Circular Waterways around Dhaka City”
BIWTA
21,125,000
$ 370,614
Jan-04
Earth filling (land reclamation by dredging) at south side of the Burigonga River using IHC Beaver 3800NG dredger by Basic Engineering - Basic Dredging JV
AGE (Army) Postogola
150,514,000
$ 2,595,068
Dec-03
Design, supply and construction of 132 KV Double Circuit Overhead Line on Towers for Re-routing of existing 132KV Bheramara-Barisal Transmission Line to By-pass Barisal Airport and existing River Crossing Portion of Turnkey basis (Contract No. 09384 dt. 05/03/2001)
Bangladesh Power Development Board
62,000,000
$ 1,068,965
Jun-03
Construction / Renovation of 132 kV Ashugonj – Mymensingh - Jamalpur Transmission Line
Power Grid Company of Bangladesh
5,203,112
$ 89,708
Mar-03
Renovation, Refurbishment and System improvement of departure floor of passenger terminal building of ZIA International Airport, Dhaka
Civil Aviation Authority of Bangladesh
123,428,728
$ 2,146,586
Jul-02
Improvement of Ground Clearance of Ashugonj-Jamapur 132 KV Double Circuit Transmission Line
Power Grid Company of Bangladesh
5,203,112
$ 90,488
Jul-02
Construction of Duct Bank, Manhole, Electrical Erection and Instrumentation work under Dhaka Grinding Plant Project (Scan Cement Industry) at Narayangonj
Korea Heavy Industries & Construction Co.(HANJUNG)
3,148,000
$ 60,538
May-01
Dhaka Grinding Plant Project, Tutki, Narayangonj
MELEC Engineering Co. Ltd.
10,425,000
$ 200,480
Feb-01
Construction/ Renovation of Ashugomj-Jamalpur 132 Kv Transmission Line (second circuit) under RRAGS (east) project
Bangladesh Power Development Board
8,837,417
$ 184,112
Dec-99
Construction and re-construction Coastal Embankment & Hydraulic Structures of Polder-59/2, Rangamati and Polder 73/1B, Hatiya, Contract:13
Bangladesh Water Development Board
370,340,454
$ 7,715,426
May-99
Construction of 132 Kv By-pass line at Barisal Airport
Bangladesh Power Development Board
2,992,805
$ 70,418
Sep-97
Construction of Related Structures of S3D, T1S 3D, T2S 3D, T3S3D, S3D, T1D, T2D, and T3D of Dinajpur canal under Teesta Barrage Project during the financial year 1994-95 & 1995-96 in Group No. 24D (Part-B)
Bangladesh Water Development Board
43,124,561
$ 1,014,695
Jun-97
65 Ft (13 pcs) Panzermast H-Pole and SumiTomo, SumiTomo, Japan
Bangladesh Power Development Board
11,370,732
$ 267,546
Feb-97
Excavation & Construction of Dinajpur Canal of Teesta Barrage Project in Group No. DC-5
Bangladesh Water Development Board
8,996,520
$ 219,427
Dec-96
Kalni-Kushiyara Pilot Dredging Project
Northeast Regional Project
53,182,625
$ 1,297,137
Sep-96
Supply, installation &b Testing of 200 KVA Diesel Generator Set at LGED HQ
LGED
2,066,000
$ 50,390
Jun-96
Bridge Construction at Somsernogor Road, Moulovibazar
Roads & Highways Department, Moulovibazar
17,938,668
$ 444,026
Oct-95
Protective work with earth, Geo-textile & CC block at Tongi-Ashulia-Savar Road
Roads & Highways Department
5,548,130
$ 137,329
May-95
Flexible pavement construction at Naogaon-AtraiNatore Road
Roads & Highways Department, Naogaon
7,999,282
$ 197,513
Oct-94
Supply & gravel laying at Hasnabad and Haripur 230 Kv Sub-station
Bangladesh Power Development Board
225,000
$ 5,555
Jul-94
Land filling work at Dhaka EPZ under work order no.: BEPZA/ CE-11/ 93/ 2257
BEPZA
9,348,000
$ 230,814
May-94
Construction of Control Room Building Equipment & Transformer Foundation, Boundary Wall, Cable Trench, Gravel Paving & Road Paving work, Foundation, construction and erection work of 02 sets 230/132 KV, 225 MVA Power Transformer work at Hasnabad and Haripur 230/132 Kv
Bangladesh Power Development Board
38,613,965
$ 953,431
Mar-94
Construction of Bhandaria 132/33 KV Sub-station and 132 KV Transmission line from Kacha River Crossing up to Bhandaria
Bangladesh Power Development Board
7,000,000
$ 172,839
Mar-94
Pavement construction at Sylhet-SalutikorKompanigonj Road
Roads & Highways Department, Sylhet
7,824,247
$ 193,191
Mar-94
Earth filling work at Haripur 230/132/33 KV Substation and construction of Embankment around the Sub-station
Bangladesh Power Development Board
25,355,322
$ 629,164
Dec-93
Hasnabad and Haripur 230/132 KV (Boundary wall, control building works, Foundation, additional wor ks) Sub-station
Lucky Engineering Co. Ltd.
38,613,965
$ 958,162
Dec-93
Sub-structure pilling work, pier work, pile cap at ODA Priority ‘B’ Bridges Contract 7, BhangaMawa Road
Roads & Highways Department
20,673,695
$ 512,994
Nov-93
Road Pavement work at Feni-Chittagong Highway
Concord-Pragatee Consortium Ltd.
25,070,500
$ 622,096
Nov-93
Earth filling by Dredger at Meghna Bridge Revetment Project
OBAYASHI CORPORATION
21,348,400
$ 529,736
Aug-93
Construction of 600 sft (10 unit) Residential Building
Bangladesh Power Development Board
3,500,000
$ 86,848
Jul-93
Reclamation of Camp yard by dredger for MeghnaGumti Bridge Construction Project
Obayashi Corporation
14,000,000
$ 347,394
Feb-93
Construction of 3-storey Residential building
Dird Private Ltd.
7,069,320
$ 176,733
Oct-92
Top