Employer |
Name & Description of work |
Date of Completion |
Bangladesh Power Development Board |
Earth filling and compacting at Haripur 230/130/132kV Sub-station, Dhaka |
Dec-92 |
Obayashi Corporation, Japan |
Earth filling and compacting for site Development work at Meghna-Gumti Bridge Construction Project by Dredger (Project of Road & Highways Department) |
Feb-93 |
Bangladesh Power Development Board |
Construction of 230/132kV Sub-station at Haripur, Dhaka (Sub-contracting to Lucky Engineering Co. Ltd., Seoul, Korea |
Sep-93 |
Bangladesh Power Development Board |
Construction of 230/132kV Sub-station at Hasnabad, Dhaka (Sub-contracting to Lucky Engineering Co. Ltd., Seoul, Korea |
Sep-93 |
Roads & Highways Department |
Construction 3rd & 4th KM flexible pavement work at Sylhet-Tamabil Road under Sylhet Road Division, Sylhet |
Feb-94 |
Bangladesh Power Development Board |
Dredging of channel in Tetulia River for placement of 33kV XLPE 2 km long cable |
Feb-94 |
Bangladesh Power Development Board |
Cable laying with XLPE Cables to cross Tetulia River on 2 channels near Dhulia, Barisal |
Mar-94 |
Bangladesh Power Development Board |
Construction of 132 kV Kacha-Bhandaria Transmission Line and 132/33kV Sub-station at Bhandaria, Pirojpur |
Sep-94 |
Roads & Highways Department |
Construction of 38.9M long (3×12.20) RCC Bridge at Moulvibazar-Shamsher Nagar Road |
Oct-94 |
Bangladesh Power Development Board |
Construction of 132 kV Sub-station including Cabling and Termination of the entire plant at Fenchuganj 90 MW Combined Cycle Power Plant |
Dec-94 |
Bangladesh Power Development Board |
Construction of 132 kV Tie-in Transmission Line at Fenchuganj 90MW Combined Cycle Power Plant |
Dec-94 |
Telephone & Telegraph Board |
PVC Duct laying works for primary cable in Chittagong Central Exchange |
Feb-95 |
Hyundai Cement (Bangladesh) Co. Ltd. |
Supply & Construction of Cement Silos, Elevated Water Tank, Foundation and Instrumentation works. |
Sep-95 |
Obayashi Corporation, Japan |
Dredging work at Meghna Bridge Protection work (Project of Roads & Highways Department) |
Aug-96 |
Bangladesh Water Development Board |
Dredging and Construction of Homestead Platform under the Kalni-Kushiyara Pilot Dredging Project in Habiganj & Kishoreganj District, Bangladesh under FAP-6 |
Aug-96 |
Teesta Barrage Project, BWDB |
Excavation and Construction of Dinajpur Canal under Teesta Barrage Project in Group No. DC-5 |
Dec-96 |
Teesta Barrage Project, BWDB |
Construction of related hydraulic structures, Group Package No. 24D (Part-B). |
Jun-97 |
Bangladesh Water Development Board |
Construction of Coastal Embankment Rehabilitation Project at Hatiya and Ramgati, Noakhali |
Jun-99 |
Power Grid Company of Bangladesh |
Construction/Renovation of Ashuganj-Jamalpur 132 kV Transmission Line (2nd Circuit) under RRAGS (East) Project |
Dec-99 |
Korea Heavy Industries & Construction Co. (HANJUNG) |
Construction of Duct Bank, Manhole, Electrical Erection and Instrumentation work under Dhaka Grinding Plant Project (Scan Cement Industry) at Narayangonj |
May-01 |
Civil Aviation Authority of Bangladesh |
Renovation, Refurbishment and System improvement of departure floor of passenger terminal building of ZIA International Airport, Dhaka |
Jul-02 |
Power Grid Company of Bangladesh |
Construction / Renovation of 132 kV Ashugonj – Mymensingh – Jamalpur Transmission Line |
Mar-03 |
Bangladesh Power Development Board |
Design, supply and construction of 132 KV Double Circuit Overhead Line on Towers for Re-routing of existing 132KV Bheramara-Barisal Transmission Line to By-pass Barisal Airport and existing River Crossing Portion of Turnkey basis (Contract No. 09384 dt. 05/03/2001) |
Jun-03 |
AGE (Army) Postogola |
Earth filling (by dredging) at south side of the Burigonga River against CA No. CEA/291 of 2000-2001, Dhaka, Bangladesh |
Dec-03 |
Mongla Port Authority |
Maintenance Dredging in the Pussur River Channel of Mongla Port of 2.8 million cubic meter |
Feb-04 |
BIWTA |
Introduction of Circular Waterways around Dhaka City, 1st Phase: Improvement of Navigation and Providing Landing Facilities from Sadarghat to Ashulia Bridge, Dhaka, Bangladesh |
Jun-04 |
Roads & Highways Department |
Improvement of 9 (Nine) Intersections in Dhaka City, Dhaka, Bangladesh, Asphalt Overlay and footpath-median development. |
Jul-04 |
Pacific Bangladesh Telecom Ltd. |
Construction of Foundation and Erection of Microwave Tower and related works, Magura, Bangladesh, Cast-in-situ bored piling of dia600mm, construction of foundation, erection of tower |
Oct-04 |
Larsen & Toubro Limited, India |
Piling work at Lafarge-Surma Cement Project, Sylhet, Bangladesh, Construction of cast-in situ bored piling work with Rotary Rig, 1200mm, 1000mm, 800mm and 600mmdia |
Dec-04 |
Roads & Highways Department |
Strengthening of existing pavement of Moulvibazar-Sreemongal, Sylhet during the year 2003-2004, Contract No. 03 (Three)/2003-2004. SE/SRC, Sylhet, Bangladesh |
Feb-05 |
Roads & Highways Department |
Strengthening of existing pavement of Moulvibazar-Srimongal-Shaistagonj-Teliapara-Jagadishpur Road (With link to Sherpur) under Moulvibazar Road Division of Sylhet Road Circle, Sylhet during the year 2003-2004, Contract No. 02 (Two)/2003-2004. SE/SRC, Sylhet, Bangladesh |
Mar-05 |
HG Power Transmission SdnBhd, Malaysia |
Construction of Barapukuria-Rangpur 132 KV Double Circuit Transmission Line |
Mar-05 |
Roads & Highways Department |
Periodic Maintenance Program 2003-PMP-2/2003-2004, Package No. PMP 2003-2004/C49 under Roads and Highways Department, Barisal, Bangladesh |
May-05 |
Executive Engineer, RHD, Road Division, Moulvibazar |
Construction of flexible pavement and earthwork at extended portion of Fenchuganh Thana Link Road under Moulvibazar Road Division |
Jun-05 |
Larsen & Toubro Limited, India |
Electrical instrumentation and installation work at Lafarge-Surma Cement Plant, Sylhet, Bangladesh |
Aug-05 |
Niko Resources (Bangladesh) Ltd. |
Construction of 3 nos. Bridge at Chhatak East Road, Chhatak Gas Field, Sunamganj. Sylhet, Bangladesh |
Sep-05 |
Niko Resources (Bangladesh) Ltd. |
Construction of 3 nos. Bridge at Chhatak East Road, Chhatak Gas Field, Sunamganj. Sylhet, Bangladesh |
Sep-05 |
Niko Resources (Bangladesh) Ltd. |
Construction of Drilling Pad of Chattak Gas Field, Sunamganj, Sylhet, Bangladesh |
Sep-05 |
Niko Resources (Bangladesh) Ltd. |
Construction of 3 (three) nos. Bridge at Chhatak East Road, Chhatak Gas Field, Sunamganj, Sylhet, Bangladesh |
Sep-05 |
Power Grid Company of Bangladesh Ltd. |
Land Development and Slope Protection work at proposed Khulna 230/132 kV Substation, Batiaghata, Khulna; Contract No. 01/PGCB/ Sec/2004/2550, Khulna, Bangladesh, Land Development work |
Oct-05 |
UNOCAL Bangladesh Ltd. |
Casing installation at Bibiyana North Pad Location, Sylhet, Bangladesh |
Oct-05 |
Roads & Highways Department |
Strengthening of existing pavement of Sylhet-Fenchuganj-RajnagarMoulvibazar-Srimongal-Shaistagonj-Teliapara-Jagadishpur Road (With link to Sherpur) under Habiganj Road Division of Sylhet Road Circle, Sylhet during the year 2004-2005, Contract No. 01 (One)/2004-2005/SE/SRC, Sylhet, Bangladesh |
Nov-05 |
Niko Resources (Bangladesh) Ltd. |
Construction of Chattak East Road, Chattak Gas Field, Sunamganj, Sylhet, Bangladesh |
Nov-05 |
Niko Resources (Bangladesh) Ltd. |
Casing Installation work at Production Pad & Relief Well of Chattak Gas Field, Sunamganj, Sylhet, Bangladesh |
Nov-05 |
Orasinvest (BD) Ltd. |
Construction of Foundation, piling work and Erection of Generator room, Shelter room, Guardroom, Boundary wall etc. for Microwave Tower and related works at Sitakunda&Wahedpur, Chittagong, Bangladesh. |
Nov-05 |
Chevron Bangladesh |
Improvement of 2 nos. LGED Bridge at Inathgonj Bazar |
Jan-06 |
UNOCAL Bangladesh Ltd. |
Strengthening of 2 (two) nos. Bridges at Bibiyana Gas Field, Sylhet, Bangladesh |
Jan-06 |
NIKO RESOURCES (BD) LIMITED |
Construction of Chattak East road |
Jan-06 |
UNOCAL Bangladesh Ltd. |
Strengthening of 2 (two) nos. Bridges at Bibiyana Gas Field, Sylhet, Bangladesh |
Jan-06 |
UNOCAL Bangladesh Ltd. |
Construction of 100 meter Oxbow lake Bridge at Bibiyana Gas field, Sylhet, Bangladesh |
Jul-06 |
UNOCAL Bangladesh Ltd. |
Construction of 100 meter Oxbow lake Bridge at Bibiyana Gas field, Sylhet, Bangladesh |
Jul-06 |
Dhaka City Corporation |
Installation of Test Pilling Work at Jattrabari-Gulistan Flyover.Dhaka, Bangladesh |
Oct-06 |
Roads & Highways Department |
Road Maintenance and Improvement Project, Dhaka-Chittagong Road, Bangladesh, Milling and cold-in situ Re-cycling and overlay works, (Total 41.38 km) |
Apr-07 |
MBEC-PBL-COPRI JOINT VENTURE |
Carrying out Cast-in situ piling (Marine) at Dapdapia Bridge, Barisal |
Oct-08 |
Roads & Highways Department |
Cast-in-situ bored piling work at Dapdapia River Bridge (Marine & Shore Piles), Barisal, Bangladesh |
Oct-08 |
Power Grid Company of Bangladesh |
Design-build and turnkey construction of 132 kV Double Circuit Aminbazar-Savar Transmission Line, length of line 25km, nos. of tower, 80 nos. |
Jul-09 |
Roads and Highways Department |
Periodic Road maintenance of Kurigram-Ulipur-Chilmari Road, Contract # PRMC-RZ-7 |
Feb-10 |
Roads and Highways Department |
Periodic Road Maintenance Component Contract # 4 for Periodic Maintenance of i) Barobari-Burimary, National Road (N509) 104,630 km under Road Network Improvement & Maintenance Project-I (RNIMP-I) |
Aug-10 |
Chevron Bangladesh |
Bibiyana Expansion Project |
Dec-13 |